I spoke with the Field team this morning. The new Oneok / TW interconnect in Ward County (POI 78161) should be available for service Monday 8/20 or Tues 8/21at the latest. The Field needs to do some final configurations to the Bristol unit over the weekend and assuming all goes well, the bi-directional point, with capacity for 200,000 MMBtu/d should be ready for service.
Kim, if you'd like, I can draft up a brief announcement for Gas Daily publication.
|