Attached is the revised regulatory matrix for Transwestern's Red Rock Expansion project reflecting the notice that tree clearing activities commenced on October 11, 2001 at Station 2. Remaining notifications include:
start of construction at remaining stations (within 10 days of start date) end of construction and in-service date (within 10 days) actual costs (within 6 months after facilities constructed) noise survey at Stations 3 & 4 (within 60 days after in-service), and any additional changes in construction and/or mitigation procedures (WOULD REQUIRE A DIRECTOR'S LETTER BEFORE IMPLEMENTING CHANGE) Any questions, let me know. Thanks for your help. Donna
|