![]() |
Enron Mail |
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii Content-Transfer-Encoding: 7bit X-From: Giambrone, Laura </O=ENRON/OU=NA/CN=RECIPIENTS/CN=LGIAMBR< X-To: Watson, Kimberly </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Kwatson< X-cc: X-bcc: X-Folder: \KWATSON (Non-Privileged)\Watson, Kimberly\Inbox X-Origin: Watson-K X-FileName: KWATSON (Non-Privileged).pst -----Original Message----- From: Mulligan, Amy Sent: Thursday, August 16, 2001 10:00 PM To: Giambrone, Laura; Hernandez, Bert; McEvoy, Christine; Miller, Beverly; Minter, Tracy; Mulligan, Amy; Ward, Linda Subject: FW: Griffith Gas & Electric Estimate - Friday Aug. 17, HE 8:00 AM to Saturday Aug. 18, HE 7:00 AM ---------- From: "Kenneth G Gruhl" <kggruhl@duke-energy.com<@ENRON[SMTP:IMCEANOTES-+22KENNETH+20G+20GRUHL+22+20+3CKGGRUHL+40DUKE-ENERGY+2ECOM+3E+40ENRON@ENRON.COM] Sent: Thursday, August 16, 2001 9:55:03 PM To: Mulligan, Amy; Allen K Nielsen; blreese@duke-energy.com; Beck Mayberry; wralkema@pplmt.com; Christopher S Smart; dacluff@duke-energy.com; dlsmith@pplweb.com; dtedesco@duke-energy.com; Schoolcraft, Darrell; Darren Stephens; David Bowers; David P Pell; George X Ouzounian; jjbischoff@pplweb.com; jmtaggart@duke-energy.com; jpritchard@citlink.net; James Stebbins; kglenny@duke-energy.com; Kim White; mschneider@duke-energy.com; Michael Kerr; Michael Wells; rjnewson@duke-energy.com; rspear@pplmt.com; Sherry Davis; Steven Fliflet; Steven Fliflet; tedmayes@aol.com; Ted Romo; Todd Hendricks; Tom Carlson; Tyler J Kristensen; ajreiter@duke-energy.com; kggruhl@duke-energy.com; pattersondw@bv.com; swansondj@bv.com Subject: Griffith Gas & Electric Estimate - Friday Aug. 17, HE 8:00 AM to Saturday Aug. 18, HE 7:00 AM Auto forwarded by a Rule Test Schedule as follows: 1) Stable Operation at Minimum load: HE 7:00 to HE 10:00 2) Stable Operation at Base Load: HE 13:00 to HE 15:00 3) Steam Turbine Trip: HE 19:00 4) Plant Shutdown HE 19:00 Note: DETM can call for more or less MW throughout the day between tests as needed. The plant shutdown will last for approximately 3 days. The scope of work is a subset of the previous planned outage worklist. Another plant shutdown will be required later to remove Steam Turbine strainers and to complete the other outage list tasks. (Embedded image moved to file: pic02082.pcx) - pic02082.pcx
|