Enron Mail

From:laura.giambrone@enron.com
To:kimberly.watson@enron.com
Subject:FW: Griffith Gas & Electric Estimate - Friday Aug. 17, HE 8:00 AM
Cc:
Bcc:
Date:Fri, 17 Aug 2001 06:26:05 -0700 (PDT)

Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
X-From: Giambrone, Laura </O=ENRON/OU=NA/CN=RECIPIENTS/CN=LGIAMBR<
X-To: Watson, Kimberly </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Kwatson<
X-cc:
X-bcc:
X-Folder: \KWATSON (Non-Privileged)\Watson, Kimberly\Inbox
X-Origin: Watson-K
X-FileName: KWATSON (Non-Privileged).pst



-----Original Message-----
From: Mulligan, Amy
Sent: Thursday, August 16, 2001 10:00 PM
To: Giambrone, Laura; Hernandez, Bert; McEvoy, Christine; Miller, Beverly; Minter, Tracy; Mulligan, Amy; Ward, Linda
Subject: FW: Griffith Gas & Electric Estimate - Friday Aug. 17, HE 8:00 AM to Saturday Aug. 18, HE 7:00 AM



----------
From: "Kenneth G Gruhl" <kggruhl@duke-energy.com<@ENRON[SMTP:IMCEANOTES-+22KENNETH+20G+20GRUHL+22+20+3CKGGRUHL+40DUKE-ENERGY+2ECOM+3E+40ENRON@ENRON.COM]
Sent: Thursday, August 16, 2001 9:55:03 PM
To: Mulligan, Amy; Allen K Nielsen; blreese@duke-energy.com; Beck Mayberry; wralkema@pplmt.com; Christopher S Smart; dacluff@duke-energy.com; dlsmith@pplweb.com; dtedesco@duke-energy.com; Schoolcraft, Darrell; Darren Stephens; David Bowers; David P Pell; George X Ouzounian; jjbischoff@pplweb.com; jmtaggart@duke-energy.com; jpritchard@citlink.net; James Stebbins; kglenny@duke-energy.com; Kim White; mschneider@duke-energy.com; Michael Kerr; Michael Wells; rjnewson@duke-energy.com; rspear@pplmt.com; Sherry Davis; Steven Fliflet; Steven Fliflet; tedmayes@aol.com; Ted Romo; Todd Hendricks; Tom Carlson; Tyler J Kristensen; ajreiter@duke-energy.com; kggruhl@duke-energy.com; pattersondw@bv.com; swansondj@bv.com
Subject: Griffith Gas & Electric Estimate - Friday Aug. 17, HE 8:00 AM to Saturday Aug. 18, HE 7:00 AM
Auto forwarded by a Rule

Test Schedule as follows:
1) Stable Operation at Minimum load: HE 7:00 to HE 10:00
2) Stable Operation at Base Load: HE 13:00 to HE 15:00
3) Steam Turbine Trip: HE 19:00
4) Plant Shutdown HE 19:00

Note: DETM can call for more or less MW throughout the day between tests as
needed.

The plant shutdown will last for approximately 3 days. The scope of work is
a subset of the previous planned outage worklist. Another plant shutdown
will be required later to remove Steam Turbine strainers and to complete
the other outage list tasks.