Kim

The level "A" (30% ?) to construct a new interconnect between TW and Questar at suction side of San Juan are as follows:

Facility requirements:

Tap/ Side-valve ( $75,000)
12" Ultra-Sonic meter
Flow control-valve with positive shut-in
Install fence-site
Meter Building
Chromatograph
EFM& SCADA

Costs:

Material costs: $240,000
Contact, inspection $135,000
Eng and project management
Contingency $50,000
OH and AFUDC $20,000

Total $520,000

If you have any questions please call.



Mansoor