Subject:TW Capacity Affected for Red Rock Tie-ins
Cc:byron.rance@enron.com, l..eisenstein@enron.com, morgan.gottsponer@enron.com,ben.asante@enron.com, darrell.schoolcraft@enron.com, jerry.graves@enron.com, rich.jolly@enron.com, earl.chanley@enron.com
Bcc:byron.rance@enron.com, l..eisenstein@enron.com, morgan.gottsponer@enron.com,ben.asante@enron.com, darrell.schoolcraft@enron.com, jerry.graves@enron.com, rich.jolly@enron.com, earl.chanley@enron.com
Date:Thu, 19 Jul 2001 14:53:48 -0700 (PDT)

The following volumes are capacities west of Station 1 that will result fro=
m tie-in construction work slated for the Red Rock expansion. Tie-in assem=
blies will be required on both the Mainline and Loopline at stations 1, 2, =
and 3. New block and side valve assemblies for new compressor and scrubber=
s will be installed on the suction side main and loop lines at each station=
. The tie-in will entail blocking (isolating) a line segment within the st=
ation yard on the suction side (each line done separately) thus creating a =
dead leg back to the next upstream block valve crossover(s). Hence, all of=
the flow will be forced into a single line when making tie-in on the adjac=
ent pipeline line. The result of forcing all volumes into a single line wi=
ll produce greater pressure losses in the operating segment to the existing=
compression and reduce throughput due to lower suction pressure and respec=
tive horsepower limitations. Discharge piping at the station having tie-in=
work will be unchanged regarding valving configurations.

Tie-in=09Schedule/Duration=09Capacity=09X-over Status
CS 2 ML=09Oct '01 / 4 days=09960 MMcfd=09MLV 3010-open us/ds x-over; open u=
s 30" x-over
CS 2 LL =09Oct '01 / 2 days=09960 MMcfd=09MLV 3010-open us/ds x-over, open =
us 30" x-over
CS 1 ML=09Mar '02=09/ 4 days=09990 MMcfd=09MLV 2012 & 2011-open us/ds x-ove=
r; open us 30" x-over
CS 1 LL=09Mar '02=09/ 2 days=09990 MMcfd=09MLV 2012 & 2011-open us/ds x-ove=
r; open us 30" x-over
CS 3 ML=09Apr '02=09/ 4 days=091010 MMcfd=09MLV 4012 & 4011-open us/ds x-ov=
er; open us 30" x-over
CS 3 LL=09Apr '02=09/ 2 days=091010 MMcfd=09MLV 4012 & 4011-open us/ds x-ov=
er; open us 30"x-over

Notes:
1.=09Specific schedule dates are forthcoming
2.=09Schedules could be impacted by material deliveries and is based upon r=
eceipt of construction permits
3.=09Durations consider working around the clock until completed