Kim-

Listed below are the issues, pretty much as written, in the meeting on the West Texas Leg. Some are self-explanatory while others are somewhat cryptic. I will follow up with a list that better defines each issue, and you might have your guys think about each as well. We'll get back together soon (I'm not sure I can do it this week), and discuss an action plan.

- CS 9 fuel
- Atoka Lateral We have both supply and market opportunities within the lateral itself
- Turbocharge the Atoka #3 units
- Look at Zia pressure obligation on the contract
- Agave replacement gas at Atoka #3
- Complete the loop between WT-1 and WT-2
- Coolers to WT-2
- Pecos compressor re-wheel and engine upgrade
- 200 300 (WT-2 to Pecos) flow study
- Look at Block Valve 16 bi-directional interconnect w/Sid Richardson, and ability flow incremental above 340 on the total system
- Look at Keystone into NNG; back to TW south of WT-2
- Check pressure of Stations 6 & 7, and PNM receipts
- MAOP restriction on Panhandle leg due to encroachment

Let's talk.