Enron Mail |
OK
-----Original Message----- From: Watson, Kimberly Sent: Wednesday, January 09, 2002 4:25 PM To: Harris, Steven; McConnell, Mark Cc: Centilli, James Subject: Trans Pecos Steve, James re-ran Trans Pecos with the following: Term: 20 years Rate: $0.261 Volume: 240,000 MMBtu/d Cost: $130.274MM (Without cost of NNG I/C and over-run up to $143.9MM) then ROE: 12.38% If Cost is capped at $130.274 (no over-run), then ROE is 15.25% --------------------------------------------------------------------------------------------------------------------------------- Term: 15 Years Rate: $0.261 Volume: 240,000 MMBtu/d Cost: $130.9 (Without cost of NNG I/C and over-run up to $143.9MM) then ROE: 10.82% If Cost is capped at $130.274 (no over-run), then ROE is 13.8% --------------------------------------------------------------------------------------------------------------------------------- Let's discuss tomorrow morning. Kim.
|