Kim

It would cost approximately $515,000 to build all the necessary interconnect facilities to deliver gas to Questar at this location( please see attached "B" release from Engineering-Roswell). Since TW is constructing this project for Questar we need to add 31.16 % tax gross-up and that will make a total cost of $ 675,427 for the project.

Again your previous cost of $702,000 , mentioned in the agreement with Questar, is fine because even "B" release cost estimates are approximately 15% ?.

If you any questions please call me at anytime.

Regards,
Mansoor


-----Original Message-----
From: Chanley, Earl
Sent: Monday, January 28, 2002 3:05 PM
To: Abdmoulaie, Mansoor
Subject: Questar I/C Estimate

Mansoor

The Questar I/C estimate for:
1) 12" hot tap on TW's 30" lateral on the suction side of Bloomfield hub
2) Measurement stations with
10" Ultrasonic tube
Flow Control
Positive Over Pressure shut-in
EFM
DAS
Chromatograph
Moisture Monitor
H2S Monitor
UPS System
Building with climate control

TOTAL COST = $515,000

Summary sheet for cost

Totals SUBTOTAL

Labor 93,677
Material 228,583
Subcontract 8,580
----------- -------
330,840 330,840


Domestic (%) Tax 6857

337,697


Material - frieght 18858
-----------
356,555


ENGINEERING (LS) 10000
Eng - Contract 6000
Eng - Construct 8565
Eng- asbuilt - AsBuiltD 4963
-----------
29528 386,083


PROJECT MANAGEMENT 7500
- Project Con 1,500 1500
-----------
9000 395,083


Construction - Managem 4800
Construction - Inspect 20000
Construction - Insp,X-Ray 2500
-----------
27300 422,383


Environmental 500
-----------
422,883


ROW Direct salaries 500
Property Purchase 3500
-----------
4000 426,883


District Labor 4800
-----------
4800 431,683

Contingency 64753
Overhead - TW (%) 9929
AFUCD 8634
-----------
83316 514,999


Total 514,999





Thanks
Earl Chanley
505-625-8031