FYI, The next Outage Coordination Commercial Review meeting is 10/11/01. The purpose for the meeting is to discuss outages that have a flow impact with the Commercial groups. Please review the attached outage report. If you have any questions or concerns, please give me a call. Jerry Graves 713-345-8923 When: October 13 Time: 1:00 to 2:00 Where: Houston 49C2 Omaha VCR - 7th floor Field Personnel - Conference # 877-795-3687 Code # 755555 Northern Border Pipeline Location Date Scope Comments CS05 10/11/01 to 10/11/01 Wash, MP2, replace their inlet air filters, and emissions test. (10 hrs) Potential impact is low. CS08 10/16/01 to 10/16/01 Wash, MP2, replace engine injectors, and emissions test. (14 hrs) Potential impact is low. CS10 10/18/01 to 10/18/01 Remove 1790-829, and install 1790-820. Emission testing. (14 hrs) Potential impact is low. CS13 10/23/01 to 10/23/01 Wash, MP2, and block valve mods. (10 hrs) Potential impact is low. CS01 10/29/01 to 10/29/01 Wash, MP2, (10 hrs) Potential impact is low. CS03 12/11/01 to 12/11/01 Wash, MP2 (10 hrs) Impact is low.
|