Below you will find a schedule for performance testing that is scheduled for Tuesday May 22, 2001 from 12:00 - 2:00. IT floor support will show up about 20 minutes prior to your groups start time and deliver you your test scripts from Monday along with clean copies for Tuesdays test.

On Tuesday we need you to repeat the test you performed on Monday May 22, 2001 as closely as possible.

Please read below for specific start times and if you have any questions contact me.

Thanks-
Georgia
x3-9974

Unify Gas Performance Testing
User Test - Schedule/Script


May 22, 2001 Begin 12:00 p.m. End 2:00 p.m. (CST)

Menu Option: Development Application / Stage Applications / Unify / Unify Gas-Power Stage
Server: SYB OFFSET Gas Stage
Data: May 17, 2001
Gas Day: May 19, 2001

Logistics (12:00 - 2:00 CST)

I.T. Team
Sitara Bridge Process - Begins @ 11:30 for gas flow on May 19th
EDI - Begins @ 12:15 Diane Niestrath will execute
all phases of EDI to generate system load. Nominations, Quick Response, and Notifications files from 01/30/01 between 10:00 and 12:00 will be processed. Scheduled Quantities will not be processed since it is not executed between 10:00 and 12:00 during bid-week.

User Team
Login 12:00 (CST)

Send EDI (users can send EDI Nominations, but will not be able to
use the Quick Response Report, or the Schedule Quantity Log - see EDI above)

Test Scripts will be distributed by the IT floor support team prior to the start of the test.

Volume Management (12:20 - 2:00 CST)

I.T. Team
POPS Revenue Bridge - Begins @ 12:20

User Team
Login 12:20 (CST)

Test Scripts will be distributed by the IT floor support team prior to the start of the test.



Settlements (1:00 - 2:00 CST)

I.T. Team
LoadRunner - The I.T. Team will evaluate the system load
between 1:00 and 1:30. If less than 100 users are logged in or the system load is determined to be low, LoadRunner scripts will begin executing at 1:30 in order to generate additional system load.

User Team
Login 1:00 (CST)

Test Scripts will be distributed by the IT floor support team prior to the start of the test.