Enron Mail |
< To: Paul Y'Barbo < < From: Chuck Thompson < < Subject: Rio Puerco Operating Issues < < < Here's the "quick and dirty" on the strategies discussed on Monday.... < < * Look at the TW 10" as the primary run..... investigate the < possibility of installing 1/4" (thickness) orifice plates in both TW < runs....If 1/4" plates are not possible, investigate meter run < change-outs....TW to speed up the pid response on the "mushroom" < regulators.... < * Take the TW "mushrooms" out of service and PNM to provide < flow-control.... take the TW positive shut-in valve out of service.... PNM < to provide shut in sequence with minimum flow parameters to be set at < approx 12,000 - 15,000 mcfd rate.... < * Investigate joint venture ultrasonic installation. < < Sorry for the delay in getting this out.... took my notebook out and put < it in my truck, son took my truck..... or if you don't like that one.... < my dog ate my papers..... had to use the paper to write an emergency note < for an elderly couple..... <
|