The balancing pool committed in the their beginning of year release to dispatch Milner as follows:
70 MW @ $0 50 MW @ $35.49 Milner has been down for maintenance until recently. Since coming back from maintenace, the 50 MW block @ $35.49 has disappeared. We analyzed the offer stack and it appears that Milner has the full 120 MW @ $0 I called Doug Heath to discuss this. He hasn't called me back. The issue I raised last week about Sherness dispatch is OK. I received a justified answer. However, this Milner issue is harder for th pool to defend. Can we pursue this. Thanks John
|